University of Colorado at Boulder
ducks at Kitteridge pond dance and theatre building window Department of Facilities Management


FM Home > Planning Home > Capital Construction >Program Planning

Program Planning Phase

 

The purpose of this phase is to describe the requirements of a proposed program of activities in such a manner that a professional consultant could prepare a proper design. The information contained in the document is also used to obtain approval to proceed, to establish the project budget and source of funding, and to provide a schedule for implementation.  The program plan does not address specific design detail; it calculates but does not dimension space; and it does not layout each and every contingency that could be encountered at some future time. It only addresses each item in a programmatic way, such as: location, type, and quantity of space to meet a specific need.  Its specific design, detailed dimensions, and its direct fit with other adjacent systems or space will be determined later after the program is laid out to scale by a project architect.

The program plan document must conform to the CCHE format and there are some differences between renovation projects and new construction.  The size and cost of the program plan will vary depending on the type of project invisioned, the size of the project, and the speed required to produce the plan.  As a rule of thumb, program plans cost between 0.3% to 0.5% of the total project cost determined in the Feasibility Study.  Renovation projects may cost more if extensive diagnostic testing is required to meet CCHE requirements. 

The average length of time that projects spend in this phase is nine months, with two additonal months required to secure campus level approvals.  Program plans have been prepared in as little as one month (though quality of the product suffered) and have taken as long as two years to write (due to unresolved political issues).   Facilities Planning recommends that program plans begin no later than September for submission to CCHE the following July.

Getting Started

Like a building, no two planning processes are exactly alike.  As the Feasibility Study is approved, Facilities Planning will sit down with representatives of the client department and work out a program planning process that is appropriate for the project being considered.  Some questions that may be discussed include:

  • How public should the process be?
  • Should the design architect be retained for the program plan? (required for renovations)
  • Is there political support for the project, both internally and externally?
  • What is the schedule for producing the program plan?
  • How much money does the department have to write the program plan?
  • How much experience does the client department have with captial construction?

Answers to these broad questions will lead to specific recommendations on the format of the planning process.

Outline of the Required Steps

As noted above, the actual process of program planning is not set in stone like the other phases described on these pages.  Instead the process is tailored to meet the needs of the proposed project.  There are steps that generally occur, as well as review requirements that happen as the plan nears completion. 

The 10 steps of the program planning process are:

Writing the Program Plan

Step 1:  Forming a Building Committee

What is required?  Facilities Planning recommends that a building committee be formed to put together the program plan.  The size and composition of the building committee will vary dependingon the type and size of the project.

Who to see?  Facilities Planning will invite the appropriate Facilities Management personnel to be on the committee and will coordinate participation from the planning consulting firm.  The client department is responsible for appointing other members of the team.

What will happen?  Facilities Planning recommends the following minimum composition to the team:

  • the client department representative;
  • the dean, director or designee of the client department;
  • the CFO of the client department;
  • the Facilities Management project planner; and
  • the program planning consultant.

This group will be the primary decision makers for the project. 

Others that might be added to the core group include

  • students;
  • faculty;
  • key staff members;
  • external advisory members;
  • CU Foundation fundraisers; and
  • allied program representatives.

Facilities Planning also recommends that a staff member be added that has experience writing material for external public consumption.  This person will develop the Institutional Goals section of the plan.  Experience has shown that the vision statements required at the beginning of a major program plan are best written by the client department, who are most aware of objectives and goals driving their project.

Step 2: Initiating the Program Planning Process

What is required:  The most successful project begin with a "kickoff" session that orients program planning participants with what will be happening throughout this phase.

Who to see:  Facilities Planning and the program planning consultant will initiate this meeting with the core team members  and other participants.

What will happen:  This meeting will be used to provide an overview of subsequent steps that will occur in the process.  Lines of communication will be drawn and concensus will be established as to how decisions about the project will be made.  Assignments will be made to people about what information they will be brining to the table.  The schedule will be reviewed to ensure that all team members are aware of deadline requirements.

Step 3: Analyzing the Project

What is required:  Each aspect of the program must be analyzed and justified to demonstrate that it conforms to CCHE guidelines and is proposed to occupy space as efficiently as possible.

Who to see:  The consulting program plan team will drive the collection of information with input fromt he core team.

What is required:  This is the heart of the matter and is often the most difficult and rewarding part of any pre-design phase.  In this step, true analysis and decision making occurs that creates a viable project.

The program plan is loosely orgainized into six sections:

  • Institutional strategic goals and objectives
  • Program goals and needs
  • Facilities response to program needs
  • Relationship to the Campus Master Plan and other projects
  • Implementation requirments (primarily cost and schedule)
  • Appendicies showing supporting data and calculations

The institutional requirements section describes how the project fits within the larger goals of the institution, both aththe campus level and at the system level. National trends in higher education and even broader perspectives can be used to demonstrate the need for a project.  Enrollment trends must be examined to determine if program growth will support expansion.  Goals and objectives should be clearly stated in visionary terms rather than deploring the state of existing facilties.  Comparative data with other institutions is often beneficial so long as it does not appear that the program is trying to "leapfrog" over those institutions to which it is being compared.

The program requirements section describes the physical needs of the program being planned, both qualitatively and quantatively.  While specific analyses will ary from project to project, a space needs analysis is teh most frequently used tool to determine program need.  Affinitities between programs are described so that relationships can be properly laid out.  Alternates to the program requirements are described to ensure that the plan selected is an appropriate response.

The facilities requirements section describes the proposed arangement of spaces usually in the form of a conceptual plan.  The conceptual plan is then test fit onto the proposed site.  General building systems are described verbally and any special requirements are noted.  A section on alternatives to the chosen facilities response is also required.

Relationship to the Campus Master Plan is used like the institutional requirements section to demonstrate that the proposed facilities response is in conformance with the master plan.  The section also descibes other projects that may be dependent upon this project or may have to occur as a part of this plan (e.g. utility expansion)

The implementation requirements section describes the cost and proposed schedule.  The cost is generated modeling the space needs analysis in the CU-Boulder Cost Model.  Facilities Planning staff will use the model to directly inform clients of the cost associated with space changes throughout the programming phase.  Planning staff will also aprise the client of the likely schedule and will note when there is potential for slippage or opportunities to improve the delivery time.

It should be noted that a financing plan is required to got to CCHE but is often included as a separate package not subject to approval by BCPC and CEC.  The funding model will need to be established with the Vice Chancellor for Administration's office, the Executive Vice Chancellor for Planning and Budget and the CU Foundation (if private donations are sought).  These financial officers will work with the Treasurer and the client to develop a funding plan for the project.  It is the client's responsibility to coordinate this aspect of the project along a parallel track to the preparation of the program plan.

The appendicies provide supplemental information for campus and state reviewers related to the project.  Examples that are required are:

  • code review;
  • space reconciliation table;
  • vicinity map
  • third party review letter

Other items that may be required include:

  • classroom calculation tables
  • detailed space needs analyis
  • space description forms
  • library space calculation tables
  • courses taught and enrollments
  • building audits

Unlike the feasibility study, a program plan must be thoroughly tested and justified.  Facilities Planning's role in this process is to challenge conventional thought to ensure that each square foot of space (and consequently each dollar) is truly needed.  This process helps ensure that the program plan will be approved by the campus and by CCHE.

Step 4:  Documenting the Plan

What is required:  The analysis portion of the plan must be documented in a CCHE format plan.

Who to see:  The program planning consultant will prepare and coordinate the various components of the plan.  Portions will be written by the client and Facilities Planning staff.

What will happen:  There will be an assignment of work early in the process.  The client will likely be responsible for much of the visionary section in the implementation requirements.  Facilities Planning will be responsible for the cost (with assistance from the consultant), schedule, master plan reconciliation tables and enrollment tables.  These are all given to the consultant for incorporation into the preliminary review draft(s).

Step 5: Preliminary Review Draft

What is required:  The consultant is required to provide at least one preliminary review draft of the main body of text not less than two weeks prior to the deadline for the final review draft.  Appendices are recommended but not required.

Who to see:  The preliminary review draft should be submitted to the Facilities Planner for distribution to the team.

What will happen:  The team will review the plan to ensure that all the material is coming together appropriately.  This is the last real opportunity for the client to review what is being written and edit the language and content that is being written.  The document should be clearly noted as the "Preliminary Review Draft"

Step 6: Final Review Draft

What is required:  Not less than three weeks before the required BCPC posting, the consultant will submit between 20 and 25 copies of the complete program plan for distribution to university reviewers.

Who to see:  Facilties Planning will handle distribution.

What will happen:  The program plan will be distributed technical staff  and administrators for their review.  The document should be clearly noted as "Final Review Draft".

Step 7:  Technical Review

What is required:  Facilties Management, ITS and EH&S staff review the program plan to ensure technical requirements are properly described in the plan.  Administrators review the plan to ensure that political concerns are well addressed.  The review period is two weeks

Who to see:  Facilities Planning will coordinate responses back from reviewers.

What will happen:  Each reviewer will make comments back on their particular area of expertise.  Most comments are solely within that area although some areas may overlap.  As comments are received, they are sent to the consultants for incorporation into the plan.  Occasionally, there are conflicting comments or ones that require some other form of arbitration.  Facilities Planning will arbitrate some of these issues and facilitate consensus.

At the end of the review period, the consultant will have approximately 5 days to incorporate the comments prior to the date of submission to the BCPC.

Step 8:  BCPC Approval

What is required:  Formal approval of the program plan is required prior to submission to the CEC for their approval.

Who to see:  Facilities Planning will place the program plan on the agenda for BCPC.  The client and consultant will give portions of the presentation.

What will happen:  The program plan will be posted on a web page or hard copy will be sent to members.   There will be a presentation at the meeting and a question and answer period for the members to ask about aspect of the plan.  A formal motion and vote will be taken.  Conditions of approval may be added to the motion for consideration by CEC.

Step 9:  CEC Approval

What is required:  Formal approval of the program plan is required prior to submission to the Chancellor for approval.

Who to see:  Facilities Planning will place the program plan on the agenda for CEC.  The Campus Architect will give the presentation, with the client in attendance for questions.

What will happen:  The program plan will be posted on a web page or hard copy will be sent to members.   There will be a presentation at the meeting and a question and answer period for the members to ask about aspect of the plan.  A formal motion and vote will be taken.  Conditions of approval may be added to the motion for consideration by CEC.

Step 10:  Chancellor's Authorization

What is required:  The Chancellor must give final authorization to proceed before a program plan leaves the Boulder campus.

Who to see:  Facilities Planning will obtain this approval prior to submitting the Regent resolution.

What will happen:  The Chancellor will review the motions and adenda that the various review committees placed on the plan.  He will then authorize Facilities Planning to submit a Regent Action Item for the project to the Board of Regents.

This completes this phase of the planning process.  Once through this stage, the project moves into the Project Approval Phase.

 



University of Colorado at Boulder gray dot
Map A to Z Index Search CU Home University of Colorado