University of Colorado at Boulder
ducks at Kitteridge pond dance and theatre building window Department of Facilities Management


FM Home > Planning Home > Capital Construction > Project Approvals


Project Approval Phase

 

The purpose of this phase is to secure the necessary university and State approvals required by statute to finance a capital construction project.  Two general approval tracks are required, one for the program plan and one for the Capital Construction Request.  These approvals frequently happen concurrently on an annual basis beginning in March.  This phase typically lasts fourteen months and may be repeated multiple times if multi-year funding is required or if a proposal is not funded in the current request year.

Expedited projects, generally auxiliary enterprises, may enter the process at anytime and generally take about six months to secure approvals.

No project may expend funds until the necessary approvals have been secured from the Board of Regents, CCHE, and the State of Colorado Legislature.

Prerequisites

No major capital construciton project can move forward until a program plan has been written, reviewed by the various campus committees, and submitted to the Chancellor for approval.  The Chancellor will make the final determination on whether a program plan should be submitted to the Board and CCHE for approval.

Outline of the Required Steps

There are 12 steps to this phase of the project:

Program Plan Approvals

Step 1:  CPC Briefing

What is required?  The Vice Chancellor for Administration will brief the Board of Regents' Capital Planning Committee on the proposed project not less than 30 days prior to when the Board is scheduled to take action on a project.  For major captial construction projects, this is typically at the April Regent Committee meeting.

Who to see?  The Vice Chancellor for Administration may request a briefing or tour of the project to better prepare for the presentation.

What will happen?  The Vice Chancellor for Administration will give  quick overview of the project to the Board of Regents, who may ask questions about the project.  Occassionally,  the board asks for additional information that is then included in the action item when submitted the next month.

Step 2:  Program Plan Approval by the Board of Regents

The program plan must be approved by the Board of Regents.

What is required?  CRS 23-1-106 requires taht the Colorado Commission on Higher Education act on program plans formally approved by governing boards.  For CU, The Board of Regents must approve the program plans prior to CCHE's review.

Who to see?  Facilties Planning will prepare the Regent Action Item and send it to the Vice Chancellor for Administration to be included in the appropriate Regent agenda packet.  The Treasurer will prepare a financial summary and action item in parallel with the program plan.

What will happen?  The agenda item will be incorporated into the Regent's packet.  This will include the budget page and the executive summary describing the project.  A separate package will be prepared by the Treasurer describing the funding mechanism and any debt that may be associated with the project.  In most cases, the Board of Regents passes the resolution approving the program plan. 

Facilities Planning also sends a copy of the program plan as a "Draft" to the CU System's Budget Director for forwarding to CCHE staff so that they may begin their review prior to action by the Regents. 

Step 3:  Program Plan Approval by CCHE

The program plan will be approved by the Colorado Commission on Higher Education after review by CCHE staff.

What is required?  C.R.S. 2-3-1304.6 requires that CCHE approve a program plan before the Legislature can act upon a funding request for a major capital construction project.

Who to see?  Approval at CCHE is handled by the CU System.

What will happen?  CCHE staff will review the program plan and develop a question list that is often returned to the campus.  Facilities Planning staff will coordinate answers from the appropriate parties and submit back to CU System and CCHE.  CCHE staff will write a summary of the project and make a recommendation for approval or denial.  The full commission will then consider the proposal and take action.  Most projects that do not require CCFE funds pass.  Those asking for State CCFE monies have a more difficult time.

Capital Construction Request

The following steps generally occur on parallel approval track to the program plan approval.

Step 4:  Campus Prioritization of Capital Construction Projects

BCPC and CEC make recommendations to the Chancellor on the priority order for projects requesting State CCFE funds.  Cash funded projects are generally not prioritized, however CCHE began requesting CFE prioritization in 2004.

What is required?  The BCPC By-laws require a public meeting in March to discuss the prioritization of capital projects.  this information is generally forwarded to the CEC for consideration at the March meeting.

Who to see?  The Project Client should plan on making a presentation to the BCPC at the March meeting.

What will happen?  Facilities Planning will prepare a draft ranking based on the ranking of projects from the previous year.  Clients for all projects will then make presentations regarding the importance of their project.  The BCPC will then discuss and make amendments to the draft list, taking a final vote to establish the list. 

This list is forwarded to CEC who may make changes to the rankings based on information available to members.  There is generally some changes through this process.  CEC then sends the final campus prioritization list to the Chancellor.  Generally, the Chancellor has accepted the list as recommended by CEC.

Step 5:  Preparation of the Five-year CIP

Facilities Planning updates the Five-year Capital Improvements Plan (CIP) based on the recommended priority.

What is required?  C.R.S. 23-1-106 requires that each institution submit a five-year capital improvements plan.  CCHE policy requires that projects be listed on the plan at least one year in advance of a capital construction request.

Who to see?  Facilities Planning prepares the CIP and coordinates with campus and CU System offices.

What will happen?  Facilities Planning staff will prepare the CIP beginning in April.  The plan will be reviewed and amended by campus administrators in May, being forwarded to CU-System for inclusion in the System Capital Construction Request Submission.  Since the CIP is submitted annually, expedited projects often require amending a previous CIP

Step 6:  Preparation of the Capital Construction Request

Facilities Planning prepares the forms required for submission to the State Legislature.

What is required?  A Capital Construction Request Form (Form CC-C) must be completed and submitted to CCHE by July 15.  Projects eligible for the Expedited Process may submit any time of year.

Who to see?  Facilities Planning prepares the CC-C form.

What will happen?  The CC-C forms will be prepared using information from the program plan.  Occassionally, additional information is needed that must be obtained from the Client program.  This form is then sent to CU System for inclusion in the University of Colorado capital construction request that includes all the other projects being submitted for the request year.

Step 7:  Approval of the CIP and Capital Construction Request by the Board of Regents

The Board of Regents approves the capital construction projects for all campuses and creates a prioritized list of all campus projects.

What is required?  The Board of Regents, as the university's governing board, must submit a five-year CIP, appropriate CC-C forms, and a ranked list of capital construction projects to CCHE.

Who to see?  The CU System's Budget Office Director prepares the information for the Board of Regents.

What will happen?  At the August meeting, the Board of Regents will act on a package prepared by the Budget Office.  Central staff will draft a priority list of university projects that may be amended by the board.  The results of the board's actions are then sent to CCHE as the official University of Colorado capital construction request.

Note that since submission to CCHE is due July 15, but the Board of Regents do not meet in July, Central submits request as a "draft" version that is amended based on the actions of the Regents at their August meeting.

Step 8:  Approval of the CIP and Capital Construction Request by CCHE

What is required?  CCHE must submit a coordinated, ranked list of higher education capital construction projects to the Capital Development Committee.

Who to see?  CU System's Budget Office Director coordinates all correspondence with CCHE during this step.

What will happen?  During July and August, CCHE staff will review the capital construction requests and create their ranked list recommendation.  This will be acted on at the September CCHE meeting and may be amended by the commission.  The final ranked list is then forwarded to the CDC.

Occassionally during the month of August, CCHE staff will submit questions that must be responded to on a tight time frame.  Facilities Planning usually coordinates the campus response to these questions.

Step 9:  Approval by the CDC

This step is iterative with the next step as OSPB adjusts revenue predictions for the upcoming fiscal year.

What is required?  The Capital Development Committee must submit to the Joint Budget Committee a list of capital construction recommendations based on available capital construction funds.

Who to see?  CU System's Budget Office Director coordinates all correspondence with the CDC during this step.

What will happen?  During October, CDC staff will review and comment on the capital construction requests using the CC-C form.  They will generate questions on the projects that are then sent to each campus.  Facilities Planning coordinates the campus responses to these questions, which usually requires a two or three day turn-around.

CDC staff then prepares a list of capital projects that should be funded based on OSPB's available revenue forecast produced in October.  The CDC then holds hearings in November where the President and the Chancellor may testify in support of the request.  A Client may also be asked to attend the hearings and speak on behalf of the project, particularly on large capital construction projects.

The CDC will then create a list of statewide capital projects to be funded that is sent to the JBC for inclusion in the Long Bill.  Projects with low rankings may fall below the anticipated revenue line and are eliminated from further consideration.

Step 10: Approval by the JBC

The Joint Budget Committee prioritizes all expenditures to be made by the state government in the upcoming fiscal year.  It may refer projects back to the CDC if revenue projections in February change the amount of funds that are anticipated.

What is required?  The JBC will hold hearings and write a funding bill  (the Long Bill) that will fund government during the upcoming fiscal year.

Who to see?  CU System's Budget Office Director coordinates all correspondence with the JBC during this step.

What will happen?  During February and March, the JBC will consider all capital construction projects.  They will then hold hearings where top CU administrators will testify on behalf of CU projects.  A Client may be asked to attend or speak at these hearings, particularly for large projects.  

The JBC then issues the Long Bill which move to the Legislature for consideration.

Step 11:  Long Bill Legislation

The full legislature must pass the funding bill for State government.

What is required?  A majority vote in favor of funding the State government is needed.

Who to see?  CU System's President's Office Director coordinates all correspondence with the Legislature during this step.

What will happen?  The Long Bill will move out of committee and into party caucuses.  It is unlikely, but possible, that a project could be cut by a party caucus. The Long Bill is then voted on by the entire House and Senate.  Once passed, it goes to the Governor's office for signature.

Step 12:  Governor's Signature

What is required?  The Governor must sign the Long Bill as the last step of enacting the legislation.

 Who to see?  CU System's President's Office Director coordinates all correspondence with the Governor during this step.

What will happen?  The Governor could take one of three actions on the Long Bill -- sign into law, veto, or line item veto out a project not to his liking.

 



University of Colorado at Boulder gray dot
Map A to Z Index Search CU Home University of Colorado